Westford, MA Development Projects: What’s Being Built in 2026

Compare five local projects, their documented milestones and the next questions to verify before buying or selling nearby.

Tracker updated November 23, 2026 · Each project retains its own evidence date

Each label describes the dated evidence below, not a claim of real-time status. Older entries identify what needs a newer record. An approval, funding award and construction start are separate milestones.

Five projects at a glance

What is happening, and what is still unconfirmed?

  • 219 Littleton Road · Westford Regency

    Under review

    Evidence: November 16, 2026

    Residential review continued; no final approval established by this agenda.

  • 70 Boston Road · Drew Farmhouse

    Approved milestone

    Evidence: April 6, 2026

    Site-work timing modification approved; unit availability unverified.

  • 50 Main Street · J.V. Fletcher Library

    Under construction

    Evidence: August 28, 2026

    Summer construction activity documented; opening information to verify.

  • 35 Town Farm Road

    Easement authorization approved

    Evidence: October 26, 2026

    Sewer easement authorization approved; execution and construction unverified.

  • 37 Powers Road

    Local approvals reported

    Evidence: March 11, 2026

    Local approvals reported for 530 apartments; construction unverified.

Considering a home near one of these projects?

If you are buying or preparing to sell, Mary can help you identify the relevant town records and questions for that address. A nearby project does not automatically predict a home’s value.

Ask Mary about a nearby project

5 of 5 entries

Residential

219 Littleton Road · Westford Regency

Under review

Evidence date: November 16, 2026

The revised Planning Board agenda lists both PB 2602 residential review and the separate PB 2605 two-lot subdivision as continued to December 7. The agenda does not establish a vote, final residential approval or a construction start.

Next thing to verify: Obtain the latest signed PB 2602 decision, approved minutes and any construction permits.

Westford Planning Board revised agenda: November 16, 2026 →

Read Mary’s project background →

Residential

70 Boston Road · Drew Farmhouse

Approved milestone

Evidence date: April 6, 2026

The Planning Board approved a site-work timing modification. This milestone does not establish that every unit is complete or available.

Next thing to verify: Confirm remaining site work, occupancy status and housing application information with the town and housing administrator.

Westford Planning Board minutes: April 6, 2026 (approved May 18) →

Municipal

50 Main Street · J.V. Fletcher Library

Under construction

Evidence date: August 28, 2026

The town’s construction updates show roof, masonry and building-system work during summer 2026.

Next thing to verify: Watch official project updates for access changes and opening information.

Westford: Library Building Project Updates →

Housing and community

35 Town Farm Road

Easement authorization approved

Evidence date: October 26, 2026

Town Meeting passed Article 8, 348–32, authorizing the Select Board to grant a sewer easement for 35 Town Farm Road. This is a utility authorization following the earlier housing funding award; it does not verify an executed easement, construction start or completed connection.

Next thing to verify: Confirm easement execution, permits and actual construction progress with the town.

Westford: October 26 Special Town Meeting results, posted October 27 →

Residential

37 Powers Road

Local approvals reported

Evidence date: March 11, 2026

The town’s 2026 Finance Committee report records final local approvals for 530 apartments in five buildings and two clubhouses. Its September 2026 building-permit and spring 2029 completion dates were the applicant’s intentions, not verified milestones. Construction status remains unverified. The separate zoning-preservation subdivision filing is not evidence that the apartment development has started.

Next thing to verify: Verify the residential decision, conditions, issued building permits and actual construction progress separately from the zoning-preservation subdivision filing.

Westford: 2026 Finance Committee report, printed page 18 →

Read Mary’s project background →

How I read a project’s progress

Proposed or under review

A concept, application or hearing establishes an idea or an active review. It does not establish final permission to build.

Approved milestone

A signed decision applies to its stated application and conditions. Other permits, funding or appeals may still matter.

Under construction

Use a dated construction record or official progress update. A rendering or projected opening date is not enough.

Entries are updated when supporting records are reviewed. This page is not an automatic town-record feed.

Have a new town record or a project question? Send it to Mary.

THE MERRIMACK VALLEY BRIEF

Housing · Community · What You Should Know

Want the useful part without following town meetings yourself?

Get The Merrimack Valley Brief once a week: housing, development and real estate changes from across the Massachusetts–New Hampshire region.

GET THE BRIEF

Sign up on Substack to receive the Brief by email. Unsubscribe anytime.